Separate the task percentage using Ms. Project

Anonymous
2016-01-21T05:19:06+00:00

Hi all, 

I would like to separate the task percentage of my project , eg.

  1. Task A -> 30% , if all task A completed, %Complete project is 30%
  2. Task B -> 40% , if all task B completed, %Complete project is 70%
  3. Task C -> 20% , if all task C completed, %Complete project is 90%
  4. Task D -> 10% , if all task D completed, %Complete project is 100%

How to make ms project could be do this without calculate of days of task ?

Thanks

Microsoft 365 and Office | Access | For home | Windows

Locked Question. This question was migrated from the Microsoft Support Community. You can vote on whether it's helpful, but you can't add comments or replies or follow the question.

0 comments No comments

5 answers

Sort by: Most helpful
  1. Anonymous
    2016-01-22T22:49:34+00:00

    Pardon me for bumping in - but you cannot have % work complete in any manner if you do not enter in "days of task." You can certainly calculate duration if you assign resources and work, but without some values - project cannot calculate % complete nor % work complete.

    You may be best with Excel and calculating your values for each Task.  You cannot calculate different values for each task (row) in Project.

    Was this answer helpful?

    0 comments No comments
  2. Anonymous
    2016-01-21T10:59:33+00:00

    Do you have a problem?

    When you say "actual work", do you mean people x hours = people hours.

    This is what MSP (and everyone) calls work. In MSP, if you assign a person at 100% to a task with duration = 1 day, where 1 day has 8 hours, then work = 8 hours. MSP has a field % work complete = actual work/work where work = actual work + remaining work.

    Three things only:

    Duration: actual, remaining, total, %

    Work: actual, remaining, total, %

    Cost: actual, remaining, total, but no % although it is easy to make one from a spare field if required

    You cannot force the summary % complete (duration) or % work complete to be what you want them to be because they are whatever they are calculated to be from the % of the tasks under each summary.

    Was this answer helpful?

    0 comments No comments
  3. Anonymous
    2016-01-21T10:49:31+00:00

    Hi,Trevor. 

    Thank you for information. I already read the article, However I mean is that percentage is not based on the duration, but the actual work completed

    Do you have a solution for my problem? 

    Thank you.

    Was this answer helpful?

    0 comments No comments
  4. Anonymous
    2016-01-21T08:37:36+00:00

    Was this answer helpful?

    0 comments No comments
  5. Anonymous
    2016-01-21T08:31:52+00:00

    You can't do this.

    This is not how it works.

    % complete = actual duration/duration where duration = actual duration + remaining duration.