We have a process here where the Designer designs something, then another Designer has to peer review it.

If you look at the image below, what I would like to do is have the start date (when the design was assigned), a due date (when the design is to be finished), then the Designer who is responsible for that specific design. The next column I want a "Review Date" (i.e., when the review has to be completed) then I want to assign the Reviewer.

Finally, in the Gantt chart, I'd like for it show the bar, then say "Corey, Tim" (Corey Designer, Tim Reviewer) since both are responsible for that design getting completed.

Right now, both the Designer and ther Reviewer columns are "Resource Name"... but I tried many different columns for the Reviewer column hoping that I can somehow put a different name in that column than the Designer column.

The closest I cam was a text field where I could manually type the name in, but then the name doesn't show up on the Gantt Chart.

In summary, I'd like for the Designer and Reviewer columns to be different, and for both names to show up the Gantt Chart ... is this possible?

Microsoft 365 and Office | Access | For home | Windows

Locked Question. This question was migrated from the Microsoft Support Community. You can vote on whether it's helpful, but you can't add comments or replies or follow the question.

0 comments No comments

1 answer

Sort by: Most helpful
  1. Anonymous
    2016-04-06T13:30:05+00:00

    The create design task and review design tasks should be on different rows - each with the designer and reviewer assigned.  The Design summary task can summarize the process.

    I hope this helps.