Hi All
I am using MS Project 2010. My project will run on 12 hr night shifts (no day shift) 7 days a week. For clarity I want to log nights (not days) on my schedule with correct start and end days and times. Shifts are 6pm to 6 am.
I don't seem to be able to set up my calendar for this arrangement.
Any help appreciated.
Thanks
Bruce
A family of Microsoft relational database management systems designed for ease of use.
Locked Question. This question was migrated from the Microsoft Support Community. You can vote on whether it's helpful, but you can't add comments or replies or follow the question.
Answer accepted by question author
Hi,
Shifts must start and finish on the same day. So your first day of the week will be 18:00 to 24:00
Second day times are:
12am to 6am and 6pm to 12am
Thanks Rod.
I thought that might be the answer but it's not what I was hoping to hear.
Regards
Bruce
Floss1954,
What exactly were you hoping for? You say you want to log nights (not days) but what exactly does that mean. If we could understand better what you want, maybe we can suggest something.
John