Hi,
I am using MS Project 2013. I need help in reference cell as we have in excel.
I want to create a custom cell that gives cell reference of start date from other row.
I am tracking a milestone in reference to start date of summary task and then will calculate variance.
Please assist.
Regards,
Alam
A family of Microsoft relational database management systems designed for ease of use.
Locked Question. This question was migrated from the Microsoft Support Community. You can vote on whether it's helpful, but you can't add comments or replies or follow the question.
All you can do is a copy then paste-link, or use VBA. Formulas in Project can't reference other tasks.