Share via

Microsoft Project 2013: Collapsing a Summary

Anonymous
2017-05-03T13:04:57+00:00

I have multiple summary tasks with a lot of sub tasks which makes my project very long. Therefore to save time scrolling, I'd like to collapse/minimize some. But my problem is when I minimize one of the summary tasks, it minimizes all of the summary tasks under it as well. I want it to only minimize its subtasks.

TIA

Microsoft 365 and Office | Access | For home | Windows

Locked Question. This question was migrated from the Microsoft Support Community. You can vote on whether it's helpful, but you can't add comments or replies or follow the question.

0 comments No comments

4 answers

Sort by: Most helpful
  1. Anonymous
    2017-05-04T16:54:55+00:00

    Hey John,

    The issue was they were not at the same outline level. Thanks for pointing that out. I now however have run into another issue with scheduling my construction project. 

    A concrete slab pour takes only one day to complete and we pour two floors a week, every Tuesday and Saturday (3-day schedule). I set up Saturday as a workday in the settings already.

    The 26th Floor is the first date (5/3/17) which I inputted manually because I need the rest of the floors to auto schedule from each other.

    In the example below, please help me figure out what my formula should be in the predecessors column and if I need any constraints.

    The first error as you can see below is on the 30th floor slab pour. The finish date needs to say "Say 5/13/17".

    Was this answer helpful?

    0 comments No comments
  2. John Project 49,710 Reputation points Volunteer Moderator
    2017-05-03T15:12:06+00:00

    Michael,

    Are "summary a" and "summary c" at the same outline level? If they are then collapsing "summary a" should not collapse "summary c". If "summary c" is at a lower outline level, then collapsing "summary a" will hide "summary c".

    What version of Project are you using? Is it updated with the latest cumulative update?

    John

    Was this answer helpful?

    0 comments No comments
  3. Anonymous
    2017-05-03T14:18:11+00:00

    John, 

    The issue I'm having in regards to your example will be when I collapse "summary a", "summary c" collapses along with it. I'd need "summary c" to stay.

    Was this answer helpful?

    0 comments No comments
  4. John Project 49,710 Reputation points Volunteer Moderator
    2017-05-03T13:44:11+00:00

    Michael,

    I'm a little confused about what you are trying to do. If you collapse a summary at outline level 1, it will collapse all tasks under it whether they are simple subtasks or other summary levels. For example, if I collapse "summary a", it will collapse tasks 1 & 2 as well as "summary b". There is no way to have only subtasks 1 & 2 collapsed and still show "summary b".

    John

    Was this answer helpful?

    0 comments No comments