What program are you using? I'm guessing Project, but I suppose it could also be excel...
gantt Chart - current date line
I have tried a few suggestions that I've read online for the last few hours. I am attempting to add a current day line to this gantt chart. I have a sample of the project tasks and the chart in the images. I can't get the line to display vertically on the chart area.
These are the tasks I have. The chart is driven off start and days.
I've toggled the series options to plot the series on secondary axis and that puts a big square on the chart.
The 0 is from trying another method to adding a vertical today line over the gantt chart.
Any help is greatly appreciated.
Microsoft 365 and Office | Excel | For home | Windows
Locked Question. This question was migrated from the Microsoft Support Community. You can vote on whether it's helpful, but you can't add comments or replies or follow the question.
2 answers
Sort by: Most helpful
-
Anonymous
2018-02-09T01:22:30+00:00 -
Vijay A. Verma 104.7K Reputation points Volunteer Moderator2018-02-09T02:02:34+00:00 I need to have a look on your workbook to provide you the right solution. This will help me to experiment and work out the solution.
Request you to please prepare and upload a sample / dummy file sans confidential / sensitive data to Onedrive and share the link? It will help me to give prompt and high quality solution.