I do not have the Inactivate Task button in MS Project 2016, not sure if its missing or if I can add it somehow. Your advice its appreciate it.

Microsoft 365 and Office | Access | For home | Windows

Locked Question. This question was migrated from the Microsoft Support Community. You can vote on whether it's helpful, but you can't add comments or replies or follow the question.

0 comments No comments

Answer accepted by question author

Vijay A. Verma 104.9K Reputation points Volunteer Moderator
2017-12-20T18:41:19+00:00

This feature is available only in Professional version of Project. Please confirm if you are having this version of MS Project (File > Account gives you this information)

Was this answer helpful?

20+ people found this answer helpful.
0 comments No comments

Answer accepted by question author

Anonymous
2017-12-20T18:42:31+00:00

Hi,

Sorry to break the bad news...but the inactivate button is only available in the Professional version.

which Version you are using?

Was this answer helpful?

10+ people found this answer helpful.
0 comments No comments

1 additional answer

Sort by: Most helpful
  1. Anonymous
    2017-12-20T18:46:17+00:00

    I have the MS Project 2016 Standard Version, which means I wont be able to use the feature.

    Thank you for the information.

    Was this answer helpful?

    5 people found this answer helpful.