Hello everybody, 

I would like to know if is it possible to split a summary task in project.

Thanks in advance

Microsoft 365 and Office | Access | For home | Windows

Locked Question. This question was migrated from the Microsoft Support Community. You can vote on whether it's helpful, but you can't add comments or replies or follow the question.

0 comments No comments

1 answer

Sort by: Most helpful
  1. John Project 49,710 Reputation points Volunteer Moderator
    2017-05-10T13:32:24+00:00

    Irene,

    Simple answer is "no", at least if you are referring to the split task function in Project.

    Please note that a summary task is not really a task at all despite the name, rather it is a summary of the tasks under it. The start of a summary line is defined by the start of the earliest subtask and the finish of a summary line is defined by the finish of the latest subtask.

    You can "split" a summary by breaking the subtasks under it into two separate summary groups. That would effectively "split" a summary task.

    Hope this helps.