Markymarek80,
Based on your description I'm trying to visualize what you have but without actually seeing your file structure, I can only guess what may be happening.
There is no problem having a project kick off milestone as the predecessor to multiple tasks and there is no problem linking that subproject kick off milestone to a kick off milestone in the master. However, if the link path ends up being duplicated through
multiple subprojects I can see the possibility of potential circular relationships if there are also links between subtasks in one subproject with those in another.
You might also see a problem is you used a template to create a series of subprojects and then attempted to insert those into a dynamic master.
If you create a very basic link structure (kick off milestone with a couple of subtasks) in a couple of simple subprojects and then create a dynamic master with its own kick off milestone, can you duplicate the error? And if so, can you send me the files
so I can take a first hand look?
John