Microsoft Project Current Date is Wrong

Anonymous
2018-05-02T13:21:54+00:00

Hello,

I am creating a Gantt Chart in Microsoft project and wish to have a Gridline showing today's date. I have done this before with no issue but in this Gantt chart today's date is showing as June 9th. Today is actually May 2nd. Any ideas on how to fix this?

Microsoft 365 and Office | Access | For home | Windows

Locked Question. This question was migrated from the Microsoft Support Community. You can vote on whether it's helpful, but you can't add comments or replies or follow the question.

0 comments No comments

1 answer

Sort by: Most helpful
  1. Anonymous
    2018-05-02T22:31:13+00:00

    Check what is the current date in project information. Usually, it takes this from the system date, but someone may have edited it. Use format, gridlines to display the current date on the chart.

    Was this answer helpful?

    6 people found this answer helpful.