Overallocation in Project
Hi,
I'm struggling with an overallocation issue on Project ; I hope to find help here.
My goal is to level a personal project, knowing the time I can put in each day.
So I created my tasks, defined their duration and predecessors. Then I created a resource (myself) with a specific calendar, that I assigned to all the tasks.
Now when I try to level the project, I get an error message :
"This overallocation cannot be resolved. [resource] is overallocated in [project] because of the combined assignments of summary task [summary task]."
It has an effect anyway but the resource is still largely overallocated with all the tasks.
Additionnal information :
- The tasks are all auto-scheduled
- 'Level only within available slack' is unchecked
- Max. Units for the resource is 100%
- All other parameters are by default to my knowledge
What did I do wrong ?
Many thanks