Hi Cassowary2203,
Thank you for query in our forum. I am very sympathetic to your experience. I do understand the inconvenience it has made and apologize for it.
As per your description*,**“* project start date and the overall percentage for that task section doesn't calculate ” .
In Microsoft Project, when you make changes to a subtask, those changes may not be reflected in the summary task for that subtask.
This problem may occur if the Calculation options for Microsoft Project setting is Manual.
If your summary tasks duration is not being updated, this may come from the project's calculation mode: perhaps it is set to manual.
Go to Tools > Options > Calculation tab and select Automatic.
Meanwhile, here is article about Percent (%) Complete fields for your reference.
If it is not your scenario, could you please explain with detail description of your scenario for better understanding your situation and suggest the better solution that satisfy your scenario.
We greatly appreciate your understanding.