I am trying to sort by task & resource name. I do this very frequently. But for some reason my "arrow" at the right of my task heading is not showing. Can anybody tell me why this might be?

Microsoft 365 and Office | Access | For home | Windows

Locked Question. This question was migrated from the Microsoft Support Community. You can vote on whether it's helpful, but you can't add comments or replies or follow the question.

0 comments No comments

Answer accepted by question author

Dale Howard [MVP] 29,860 Reputation points MVP Volunteer Moderator
2019-08-20T16:48:26+00:00

RL3506 --

Click the View tab to display the View ribbon in Microsoft Project.  In the Data section of the View ribbon, click the Filter pick list and select the Display AutoFilter item near the bottom of the menu.  This option is what displays the arrow button in the column header of every column.  Hope this helps.

Was this answer helpful?

6 people found this answer helpful.
0 comments No comments

2 additional answers

Sort by: Most helpful
  1. Anonymous
    2019-08-20T17:39:19+00:00

    Thank you Dale! That did it. Very much appreciated.

    Was this answer helpful?

    0 comments No comments
  2. Anonymous
    2019-08-20T16:36:19+00:00

    Hi. RL3506

    My name is Anthony, an Independent Advisor trying to help.

    In this case, to order tasks, resources or dates, I leave the following information from our community link to address your problem, if these processes still present the problem we are here to help:

    https://support.office.com/en-us/article/sort-t...

    Best Regards.

    Anthony. -

    Was this answer helpful?

    0 comments No comments