Auto-Populate Dates

Anonymous
2019-06-06T17:53:00+00:00

Hello,

I am trying to have project tasks auto populate the start and end date based off of the project end date.

For example:

Go-Live Date: October 31st

Functional Testing: needs to be completed 30 days prior to end date (go-live date); takes 10 weeks to complete

  • I would like the dates for functional testing to autopopulate based on the go-live date
Microsoft 365 and Office | Access | For home | Windows

Locked Question. This question was migrated from the Microsoft Support Community. You can vote on whether it's helpful, but you can't add comments or replies or follow the question.

0 comments No comments

3 answers

Sort by: Most helpful
  1. John Project 49,710 Reputation points Volunteer Moderator
    2019-06-06T18:50:53+00:00

    Ashley,

    You're welcome. If I answered your question, please consider marking my response as the answer.

    As long as you have Project set for auto-scheduling and all your tasks are linked in a logical sequence of performance with appropriate dependencies, Project will automatically calculate the start and finish dates. Never directly enter dates as that sets a constraint and effectively negates Project's scheduling engine.

    John

    Was this answer helpful?

    1 person found this answer helpful.
    0 comments No comments
  2. Anonymous
    2019-06-06T18:34:08+00:00

    Thank you very much! We can definitely do it from the start date! We want to use our project plan as a template because all of our projects are a standard 16 weeks. So I was just trying to find a way that would auto populate dates based on the start or finish date.

    Edit: How did you get the dates to autofill? Did you link the tasks together and then did the equation?

    Ashley

    Was this answer helpful?

    0 comments No comments
  3. John Project 49,710 Reputation points Volunteer Moderator
    2019-06-06T18:14:21+00:00

    anharris90,

    Although scheduling from a finish date may seem like a logical approach when you have a fixed end date, in practicality, it is fraught with frustration. (Try to say that 10 times fast.)

    However, assuming you have set the Project to schedule from the finish date and set the finish date as 10/31/19, this is one way to get there.

    I think most of us who have worked with Project for years will suggest you always schedule in a forward manner (i.e. from the start date). Lay out the plan in a logical sequence. Does it meet the desired end date? If not, re-plan until it does, or, recognize the plan is simply not achievable.

    Hope this helps.

    John