Hi,
Specific time scheduling (e.g. 8:30-9:30 AM task assignment) has been solved.
However, I'm still struggling with managing multiple projects with a Sharepoint synchronization. The situation is this:
- We have 10 Project managers
- We have 40 Projects, therefore 1 Project manager has multiple projects.
- We have 50 Employees that work on 40 projects.
- These projects are not linked to each other.
Question 1: How do I set up the projects in Sharepoint in a way that the 'Resource pool' of 50 employees is being shared by all projects? What i mean by this is, that a project manager can't use a resource if it is already booked. (In MS Project Desktop,
this would be the Red mark on a resource). Currently I'm only able to do 40 different "Project sites". I need this to be combined somehow.
Case example: Project manager schedules John Smith for 4.12.2020 8-12:00am for Project 283. John is already booked during that time for Project 288. The project manager should be blocked or receive a signal that he cannot book John.
Question 2: How do i set up the projects so that i can tell each employee all the tasks he/she is assigned to? This needs to be one report, that tells what he/she has been assigned to, no matter what the project is.
Case example: John works on multiple projects next monday. He needs to have a clear list of what he will be working on:
| Project |
Time |
Task |
| 283 |
4.12.2020 8-12:00AM |
Clean surfaces |
| 288 |
4.12.2020 12-2PM |
Make measurements |
| 288 |
4.12.2020 2-4PM |
Document findings |
Regarding the possible solutions: I wish Sharepoint could solve these. However, PowerBI can be utilized and i have VBA experience. However, VBA should be the last resort..
Thank you for the assistance!