If it gives this error, then there is definitely some circular links in there somewhere. They can be hard to track down, especially if there are many tasks and numerous predecessors/successors, and especially if there are other than FS0 links (FF, SS, SF) with positive or negative lag.
We don't know how many tasks or how complicated the predecessors/successors are, so it is a bit difficult to help without seeing more.
It helps to have both the predecessor and successor columns side by side.
Also, view, details will split the screen and the right click menu will allow to display predecessors and successors in the lower pane..
Of course, summaries should (must) not have predecessors or successors.