Share via

MS Project Calculating Duration Incorrectly

Anonymous
2022-05-22T15:32:28+00:00

When I set a fixed duration task to start on 5/25 and finish on 6/7, this is a duration of 10 days. MS Project for some reason however, is displaying a duration of 12 days. This is incorrect. I don't' understand why its doing this. If I manually change the duration field to 10 days, then project changes the finish date to 6/6, which is still not correct because working days from 5/25 to 6/6 would be 8 days. I have May 30th scheduled as a non-working day for memorial day. I'm not sure if it has anything to do with the options I have set for the project which is 6 hours per day, 30 hours per week to account for the reality that its not realistic for someone to be able to dedicate a full 8 hour day to project work. See screenshot.

Microsoft 365 and Office | Project | For home | Windows

Locked Question. This question was migrated from the Microsoft Support Community. You can vote on whether it's helpful, but you can't add comments or replies or follow the question.

0 comments No comments

1 answer

Sort by: Most helpful
  1. John Project 49,715 Reputation points Volunteer Moderator
    2022-05-22T20:16:08+00:00

    JBLT83,

    Please do not cross-post. I already answered your question on the Tech Community forum.

    John

    Was this answer helpful?

    0 comments No comments