Share via

Make the Effort Calculation Optional

Paul Juska 0 Reputation points
2025-12-02T16:42:29.03+00:00

Planner: Show of hands - who would like to see the Task Effort calculation based on Duration be OPTIONAL. If I give a resource 10 days to complete a 4 hour task, I don't want to see 80 hours in the effort field. I know I could work around by making the start and end date the same date and enter .5 in the duration, but I need to manage resources by weeks and months, not day by day. i.e. how many hours of work have we assigned Bob this month? Just give me a button to "Enter effort manually"

Microsoft 365 and Office | Other
0 comments No comments

1 answer

Sort by: Most helpful
  1. Anonymous
    2025-12-02T17:16:51.4033333+00:00

    Hi there, I understand how this can catch you off guard when the numbers don’t match what you expect.

    What’s happening is that the system automatically calculates effort based on the task duration and the resource’s availability, so if a task spans 10 days, it assumes full-time work across that period.

    To fix this, you can either adjust the duration to match the actual work time or split the task into smaller chunks, so the effort reflects reality.

    Could you tell me if you need the timeline to stay at 10 days for scheduling purposes, or is the main goal to keep the effort accurate for reporting?

    That will help me guide you to the best option.

    Regards,
    Aron

    Was this answer helpful?

    0 comments No comments

Your answer

Answers can be marked as 'Accepted' by the question author and 'Recommended' by moderators, which helps users know the answer solved the author's problem.