Reporting - Sprint 157 Update

Features

Lead and Cycle Time widgets advanced filtering

Lead and cycle time are used by teams to see how long it takes for work to flow through their development pipelines, and ultimately deliver value to their customers.

Until now, the lead and cycle time widgets did not support advanced filter criteria to ask questions such as: "how long is it taking my team to close out the higher priority items?"

With this update questions like this can be answered by filtering on the Board swimlane.

Lead and Cycle Time widgets advanced filtering.

We've also included work item filters in order to limit the work items that appear in the chart.

Work item filters to limit the work items that appear in the chart.

Next steps

Note

These features will roll out over the next two to three weeks.

Head over to Azure DevOps and take a look.

How to provide feedback

We would love to hear what you think about these features. Use the help menu to report a problem or provide a suggestion.

Make a suggestion

You can also get advice and your questions answered by the community on Stack Overflow.

Thanks,

Aaron Hallberg