Project schedule API performance

Applies To: Project Operations Integrated with ERP, Project Operations Core, Project for the web

This article provides information about the performance benchmarks of the Project schedule application programming interfaces (APIs) and identifies the best practices for optimizing usage.

Project Scheduling Service

The Project Scheduling Service is a multitenant service that runs in Microsoft Azure. It's designed to improve interaction by providing a fast and fluid experience when users work on projects. This improvement is achieved by accepting change requests, processing them, and then immediately returning the result. The service asynchronously persists to Dataverse and doesn't block users from performing other operations.

The Project schedule APIs rely on the Project Scheduling Service to run requests. Later sections of this article describe these requests in more detail.

The Project schedule APIs are designed to work with the following work breakdown structure (WBS) entities:

  • Project
  • Project Task
  • Project Task Dependency
  • Project Team Member
  • Resource Assignment

Both out-of-box fields and custom fields are supported. Unless otherwise noted, all common operations are supported, such as create, update, and delete. For more information, see Use Project schedule APIs to perform operations and scheduling entities.

As part of the Project schedule APIs, a unit-of-work pattern is added. This pattern is known as an OperationSet, and you can use it when you need to process several requests in a single transaction.

The following illustration shows the flow that a partner experiences when this feature is used.

Screenshot of Dataverse and project scheduling service flow.

Step 1: A client makes an API call to an Open Data Protocol (OData) endpoint ExecuteOperationSetV3. This call does the following actions:

  1. Creates an OperationSet.
  2. Loads the OperationSet with Project schedule API requests.
  3. Sends all the changes to Project Scheduling Service in one batch.

The Project Scheduling Service runs its own validations on requests in the batch. Any validation failures undo the batch and return an exception to the caller. If the Project Scheduling Service successfully accepts the batch, it updates the OperationSet status to reflect that it's processing the OperationSet.

Step 2: This step represents the PERSIST phase. The Project Scheduling Service asynchronously writes the batch to Dataverse in a transaction. If the write operation is successful, the OperationSet is marked as Completed. Any errors roll back the transaction and the batch, and the OperationSet is marked as Failed.

Performance methodology

You run all operations a combined 2,280 times and report the P90 execution time measurements. Measure single-record and bulk operations.

For a single-record operation, the OperationSet contains one request. For bulk operations, it contains 20, 50, or 100 requests. Report each bulk size separately.

Run these operations on a UR58 Project Operations Core distributed across North America, EMEA, and APAC.

Results

Single-record operations

The following table shows the execution times for the creation, update, and deletion of a single record. The times are in seconds.

Schedule API Duration: Time taken by ExecuteOperationSetV3

Total Duration: Schedule API duration + Project Save Service time + time taken to sync to Dataverse

Operation Record type Schedule API Duration - Required fields Schedule API Duration - All supported fields Total Duration - Required fields Total Duration - All supported fields
Create Project 2.18 2.41 2.18 2.41
Create Task 1.67 1.73 7.86 12.63
Create Assignment 1.46 2.03 10.86 12.81
Create Dependency 1.43 1.55 9.07 10.35
Update Project 1.56 1.59 7.91 11.00
Update Task 1.51 1.72 7.79 18.72
Update Team Member 1.94 1.92 10.71 9.37
Delete Task 1.53 1.55 7.92 9.68
Delete Assignment 1.44 1.44 7.89 9.36
Delete Dependency 1.23 1.44 8.88 8.40
Delete Team Member 1.41 1.49 9.91 10.97

Note

  • The Team Member entity isn't included in the create operation, because you can create a Team Member directly in Dataverse.
  • Update operations on the Resource Assignments and Project Task Dependency entities aren't supported.
  • Delete operation on the Project entity isn't supported.

Bulk operations

The following table shows the execution times for the creation, update, and deletion of many records. Specifically, Microsoft measured the execution times for the creation of 20, 50, and 100 records in a single OperationSet. The times are in seconds.

Schedule API Duration: Time taken by ExecuteOperationSetV3

Total Duration: Schedule API duration + Project Save Service time + time taken to sync to Dataverse

Operation Record type No. of Records Schedule API Duration - Required fields Schedule API Duration - All supported fields Total Duration - Required fields Total Duration - All supported fields
Create Task 20 1.88 2.81 9.57 32.75
Create Task 50 2.41 3.17 12.82 36.96
Create Task 100 4.14 3.97 15.96 47.55
Create Assignment 20 2.61 1.98 12.51 26.62
Create Assignment 50 2.49 2.73 18.49 62.40
Create Assignment 100 3.85 4.04 35.43 68.69
Create Dependency 20 1.71 1.92 8.91 19.92
Create Dependency 50 2.38 2.58 18.72 39.73
Create Dependency 100 3.45 4.80 41.29 83.41
Update Task 20 2.03 5.36 8.82 20.42
Update Task 50 3.72 11.97 30.37 64.36
Update Task 100 5.94 20.21 69.37 155.52
Update Team Member 20 2.17 3.86 15.01 12.61
Update Team Member 50 3.88 6.33 17.89 21.84
Update Team Member 100 6.39 12.40 30.23 31.85
Delete Task 20 1.62 1.66 13.40 24.33
Delete Task 50 2.25 2.46 33.75 54.92
Delete Task 100 3.20 3.28 73.90 110.70
Delete Assignment 20 1.55 1.58 8.69 13.98
Delete Assignment 50 2.06 2.38 15.87 23.17
Delete Assignment 100 3.04 3.62 39.27 54.76
Delete Dependency 20 1.57 1.80 11.49 13.73
Delete Dependency 50 2.24 2.53 19.40 45.26
Delete Dependency 100 3.31 3.73 31.56 48.14
Delete Team Member 20 2.05 2.19 13.67 15.09
Delete Team Member 50 3.35 3.16 20.62 22.58
Delete Team Member 100 4.18 5.15 25.49 36.66

Note

  1. The table doesn't include bulk create operations on the Project and Team Member entities, because the runtime for those operations resembles the runtime when the API for creating a single record is called multiple times. These APIs run immediately in Dataverse.
  2. Update operations on the Resource Assignments and Project Task Dependency entities aren't supported.
  3. Delete operations on the Project entity aren't supported.

Best practices

Based on the preceding scenario results, the APIs perform better in the following conditions:

  • Use the latest versions of the Schedule APIs as they're optimized for better performance.
  • Group as many operations together as possible. The average runtime for bulk operations is better than the average runtime for single-record operations. The smaller the number of operation sets in use, the faster the average execution time is.
  • Set only the minimum attributes that are required to accomplish your scenario. Be selective about the types of nonrequired fields included in an operation set request. Fields that contain foreign keys or rollup fields negatively affect performance.