Define working hours by day that vary for each project

Important

This content is archived and is not being updated. For the latest documentation, go to Project Operations updates. For the latest release plans, go to Dynamics 365, Power Platform, and Cloud for Industry release plans.

Enabled for Public preview General availability
Users by admins, makers, or analysts - Sep 6, 2023

Business value

This feature provides the ability to define working hours by day for each project so projects that are delivered in different regions can plan schedules and resource capacity based on the practices in their region.

Feature details

With the release of this feature, an organization can define the default behavior of the duration field on a task when calculating how many hours are in a day, a week, or how many days are assumed in a month. This feature will also support the ability for this precision to be adjusted on a project basis by the project manager.

See also

Define resource calendars (docs)