Set up warehouses for transfer orders

You can use warehouse levels to create a hierarchy that supports transfer orders between warehouses. Based on this setup, master scheduling calculates item requirements at the individual warehouse level and generates planned transfer orders from an assigned source warehouse to fulfill them.

  1. Click Inventory management > Setup > Inventory breakdown > Warehouses.

  2. Select the warehouse that you want to refill.

  3. On the Master planning FastTab, select the Refilling check box.

  4. In the Main warehouse field, select the warehouse that you want to assign as the refilling warehouse. Master scheduling calculates a transfer requirement for the selected warehouse and generates a planned transfer order from the assigned Main warehouse.

    Note

    If you clear the Refilling check box, the selected warehouse is assigned a warehouse level in regard to the Main warehouse, but the Main warehouse is not set up as a refilling warehouse.

  5. Close the page to apply the new setup.

Tip

If you want to assign a warehouse for refilling, you must first set up the warehouse as a storage dimension on the Storage dimension groups page. On this page, select the Active field and the Coverage plan by dimension field for the warehouse.

Set up transport lead time

You must also set up the transport lead time between the warehouses on the Transport days page.

  1. Go to Inventory management > Setup > Distribution > Transport days.
  2. In the Receiving point field, select warehouse.
  3. Select the Shipping warehouse, Receiving warehouse, and Transport days.
  4. (Optional) You can also set transport time, depending on the mode of delivery, under the Transport days per mode of delivery tab.