ACWP is the actual cost of work performed up to the project status date or the current date.

For a Task, ACWP is the costs incurred for work already done on a task.

For a Resource, it is the sum of ACWP values for all of a resource's assignments.

For an Assignment, it is the costs incurred for work already performed by a resource on a task.

<ACWP>
  FloatValue
</ACWP>

Parent Elements

TaskResourceAssignment

Occurrences

Minimum: 0

Maximum: 1