Finish Element

For a Task, Resource, or Assignment element, Finish is the date and time that a task is scheduled to be completed.

For a Baseline element, it is the scheduled finish date of the task, resource, or assignment when the baseline was saved.

For a TimephasedData element, it is the finish date of the timephased data period in the task, resource, assignment, or baseline.

For Sprints, the finish date of the sprint.

<Finish>
  DateTimeValue
</Finish>

Parent Elements

Occurrences

Minimum: 0

Maximum: 1

See Also

Concepts

Task Elements and XML Structure

XML Schema for the Tasks Element

Assignment Elements and XML Structure

XML Schema for the Resources Element

Assignment Elements and XML Structure

XML Schema for the Assignments Element

TimephasedDataType Elements and XML Structure

XML Schema for the TimephasedDataType Complex Type