FinishVariance Element

For a Task, FinishVariance is the amount of time that represents the difference between a task's baseline finish date and its current finish date.

For an Assignment, it is the difference between an assignment's baseline finish date and its scheduled finish date.

<FinishVariance>
  IntegerValue
</FinishVariance>

Parent Elements

TaskAssignment

Occurrences

Minimum: 0

Maximum: 1

See Also

Concepts

Task Elements and XML Structure

XML Schema for the Tasks Element

Assignment Elements and XML Structure