LevelingDelay Element

For a Task, LevelingDelay is the amount of time that a task is to be delayed from its early start date as a result of resource leveling.

For an Assignment, it is the total amount of work scheduled to be performed by a resource on a task.

<LevelingDelay>
  IntegerValue
</LevelingDelay>

Parent Elements

TaskAssignment

Occurrences

Minimum: 0

Maximum: 1

Remarks

A LevelingDelay requires the LevelingDelayFormat to be specified. For example, a leveling delay of 3 days in a task is expressed as follows:

<Task>
    ...
    <LevelingDelay>3</LevelingDelay>
    <LevelingDelayFormat>7</LevelingDelayFormat>
    ...
</Task>

See Also

Reference

LevelingDelayFormat Element

Concepts

Task Elements and XML Structure

XML Schema for the Tasks Element

Assignment Elements and XML Structure

XML Schema for the Assignments Element