MoveCompletedEndsForward Element

Indicates whether the end of completed portions of tasks scheduled to have been completed before the status date, but begun late, should be moved up to the status date.

<MoveCompletedEndsForward>
  BooleanValue
</MoveCompletedEndsForward>

Parent Elements

Project

Occurrences

Minimum: 0

Maximum: 1

Text Value

A text value of type boolean is required.

Value

Description

0

False

1

True

Remarks

The MoveCompletedEndsForward element has a rounding error. The internal work value has eight digits; the work value loses 0.001 seconds for every minute, causing a rounding error.

See Also

Concepts

Project Elements and XML Structure

XML Schema for the Project Element