OvertimeWork Element

For a Task, OvertimeWork is the amount of overtime scheduled to be performed by all resources assigned to a task and charged at overtime rates.

For a Resource, it is the amount of overtime to be performed for all tasks assigned to a resource and charged at the resource's overtime rate.

For an Assignment, it is the amount of overtime to be performed by a resource on a task; charged at the resource's overtime rate.

<OvertimeWork>
  DurationValue
</OvertimeWork>

Parent Elements

TaskResourceAssignment

Occurrences

Minimum: 0

Maximum: 1

See Also

Concepts

Task Elements and XML Structure

XML Schema for the Tasks Element

Resource Elements and XML Structure

XML Schema for the Resources Element

Assignment Elements and XML Structure