RemainingCost Element

For a Task, RemainingCost is the remaining scheduled expense of a task that will be incurred in completing the remaining scheduled work by all resources assigned to a task.

For a Resource, it is the remaining scheduled expense that will be incurred in completing the remaining work assigned to a resource.

For an Assignment, it is the costs associated with completing all remaining scheduled work by any resources on a specific task.

<RemainingCost>
  DecimalValue
</RemainingCost>

Parent Elements

TaskResourceAssignment

Occurrences

Minimum: 0

Maximum: 1

See Also

Concepts

Task Elements and XML Structure

XML Schema for the Tasks Element

Resource Elements and XML Structure

XML Schema for the Resources Element

Assignment Elements and XML Structure