RemainingWork Element

For a Task, RemainingWork is the total amount of non-overtime work scheduled to be performed by all resources assigned to a task.

For a Resource, it is the amount of time, or person-hours, still required by a resource to complete all assigned tasks.

For an Assignment, it is the amount of time required by a resource assigned to a task to complete an assignment.

<RemainingWork>
  DurationValue
</RemainingWork>

Parent Elements

TaskResourceAssignment

Occurrences

Minimum: 0

Maximum: 1

See Also

Concepts

Task Elements and XML Structure

XML Schema for the Tasks Element

Resource Elements and XML Structure

XML Schema for the Resources Element

Assignment Elements and XML Structure

XML Schema for the Assignments Element