StartVariance Element

For a Task, StartVariance is the difference between a task's baseline start date and its currently scheduled start date.

For an Assignment, it is the difference between an assignment's baseline start date and its currently scheduled start date.

<StartVariance>
  IntegerValue
</StartVariance>

Parent Elements

TaskAssignment

Occurrences

Minimum: 0

Maximum: 1