Summary Element

Indicates whether the task is a summary task or the assignment is on a summary task.

<Summary>
  BooleanValue
</Summary>

Parent Elements

Assignment, Task

Occurrences

Minimum: 0

Maximum: 1

Text Value

A text value of type boolean is required.

Value

Description

0

False

1

True

Remarks

Note

You should generally assign resources to individual subtasks, not to a summary task. For more information, see Assign a resource to a task in the Project 2007 Help and How-to guide.