WorkVariance Element
For a Task, WorkVariance is the difference between a task's baseline work and the currently scheduled work.
For a Resource, it is the difference between a resource's total baseline work and the currently scheduled work.
For an Assignment, it is the variance of assignment work from the baseline work, expressed as minutes x 1000.
<WorkVariance>
FloatValue
</WorkVariance>
Parent Elements
Occurrences
Minimum: 0 Maximum: 1 |
See Also
Concepts
Task Elements and XML Structure
XML Schema for the Tasks Element
Resource Elements and XML Structure
XML Schema for the Resources Element