Application.ChangeStatusDate method (Project)
Changes the project status date.
Syntax
expression. ChangeStatusDate
( _Date_
)
expression An expression that returns an Application object.
Parameters
Name | Required/Optional | Data type | Description |
---|---|---|---|
Date | Optional | Variant | New date for the project status date. |
Return value
Boolean
Remarks
The project status date enables Project to show progress lines in tasks on the Gantt chart. The status date is also used in earned value calculations. Using ChangeStatusDate with no parameter shows the Status Date dialog box. If the user cancels the dialog box, ChangeStatusDate returns False.
Example
The following example changes the project status date to April 7, 2012.
ChangeStatusDate("4/7/12")