Application.LinksBetweenProjects method (Project)

Specifies whether the Links between Projects dialog box appears when opening a project containing cross-project links.

Syntax

expression. LinksBetweenProjects( _AcceptAll_ )

expression A variable that represents an Application object.

Parameters

Name Required/Optional Data type Description
AcceptAll Optional Boolean True if all changes to external predecessors and successors are accepted. False if the Links between Projects dialog box appears. The default value is False.

Return value

Boolean

Support and feedback

Have questions or feedback about Office VBA or this documentation? Please see Office VBA support and feedback for guidance about the ways you can receive support and provide feedback.