PJTaskOutlineShowLevel enumeration (Project)

Contains constants that specify the task outline levels to display.

Name Value Description
pjTaskOutlineShowLevel1 1 Display level 1.
pjTaskOutlineShowLevel2 2 Display levels 1 and 2.
pjTaskOutlineShowLevel3 3 Display levels 1 through 3.
pjTaskOutlineShowLevel4 4 Display levels 1 through 4.
pjTaskOutlineShowLevel5 5 Display levels 1 through 5.
pjTaskOutlineShowLevel6 6 Display levels 1 through 6.
pjTaskOutlineShowLevel7 7 Display levels 1 through 7.
pjTaskOutlineShowLevel8 8 Display levels 1 through 8.
pjTaskOutlineShowLevel9 9 Display levels 1 through 9.
pjTaskOutlineShowLevelMax 65535 Display all levels.

Support and feedback

Have questions or feedback about Office VBA or this documentation? Please see Office VBA support and feedback for guidance about the ways you can receive support and provide feedback.