Listing the project tasks and owners

Based on the five project phases (planning, designing, making, testing, and deploying and refining), list the tasks that need to be done during each phase. Assign who will be responsible for each task, along with the targeted date of completion.

You might want to use Microsoft Planner to manage your tasks together with your project team.

See Developing solutions collaboratively for information about how to enable multiple people to build one Power Apps project.

Example: Expense report project tasks and owners

Abhay, who has visibility across the whole process and a passion for solving this problem, is taking the lead on this project.

Task Owner Target date
Create the project plan and get it approved by sponsors Abhay January 15
Identify users for testing, and schedule their time Nick February 1
App screen design complete and signed off Abhay February 1
Make expense report create/view app Gibson February 15 (ready for testing)
User testing for create/view app Nick February 15 to February 22
Make approval process Abhay February 15 (ready for testing)
Provide BI report requirements to the team for phase 2 Charlotte February 15
Create an updated process explainer for managers to use with employees Nick February 15
Auditor sign-off on business rules and report storage implementation Rebecca February 22
Roll out expense report create/view app in production Gibson March 15