Configure working days
Azure DevOps Services | Azure DevOps Server 2020 | Azure DevOps Server 2019 | TFS 2018 - TFS 2013
Configure the days that your team works. Your team's working days aid in capacity planning purposes and when you're using sprint and scrum methods in Azure Boards. Each team's sprint planning and tracking tools automatically consider days off when calculating capacity and sprint burndown. Leave those days of the week that your team doesn't work unchecked.
Note
The Working days setting specifies the days that teams regularly take off each week. To specify additional non-working days off, such as holidays or a team day off, set these through the Capacity page as described in Set sprint capacity, Set capacity for the team and team members.
Prerequisites
- To configure team settings, you must be added as a team administrator or be a member of the Project Administrators group. See Change project-level permissions.
Set working days
To set non-working days, modify the ProcessConfiguration file. For details, see Process configuration XML element reference, Set non-working days.