Rolled-up Cost Shares Report

Shows a list of the rolled-up cost shares of the individual assembly or production BOM items.

You get a detailed report of items in the BOM, their quantity and their cost shares specified in material, capacity, overhead and total cost for each item.

Important

To base the report on the latest component costs, you must first go to the item card of the parent item to update the standard cost of its components. For more information, see How to: Calculate the Standard Cost of Assembly BOMs. The procedure is similar for production BOMs.

The rolled-up costing method means that material cost is calculated as the cost of all items in the parent item's product structure. Capacity and subcontractor costs are calculated as the costs related to produce all of the items in the parent item's product structure.

Options

Calculation Date: Enter the date you want the cost shares to be calculated.

Tip

For more information on how to work with reports, see Viewing Test Reports before Posting, How to: View and Print Reports and How to: Set Filters. For assistance in finding specific pages, see Search.