Send-Ahead Quantity Field, Routing Line Table

Specifies the send-ahead quantity. The send ahead quantity is the movement of a portion of a lot of material to a subsequent operation before completion of the current operation for all units of the lot. The purpose of sending material ahead is to reduce the manufacturing lead-time. The next operation is started when the send ahead quantity is produced.

Use the following formula to calculate the send-ahead quantity: Start of the next operation = setup time + send ahead quantity * run time + wait time + move time + queue time (at next operation).

Example:

If 10 parts have been determined as a send-ahead quantity, the next operation can begin when these 10 parts have been finished in the actual operation.

Start of the next operation = 10 minutes setup time + (10 pieces * 5 minutes run time) + 5 minutes wait time

As a result, the next operation can be started 65 minutes after the actual operation starts.

Tip

For more information on how to work with fields and columns, see Work with Data. For assistance in finding specific pages, see Search.

Parent Tables

Table Location
Routing Line Table Manufacturing
Routing Line Table Manufacturing

See Also

Reference

Routing

Other Resources

How to: Create Routings