Specifies in which order operations in the routing are performed.
Options
Option | Description |
---|---|
Serial |
Specifies that operations are performed consecutively. When the production order routing is calculated, operations are ordered according to the value in the Operation No. field on the routing line. |
Parallel |
Specifies that two operations can be performed at the same time. When the production order routing is calculated, operations are ordered according to the value in the Next Operation No. field on the routing line. |
Example of Parallel Routing
After operation 10, the next sequential operation, 20, must not follow. Instead, operations 20 and 30 must follow in parallel. This is set up on a serial routing by entering 20|30 on the second routing line.
Tip
For more information on how to work with fields and columns, see Work with Data. For assistance in finding specific pages, see Search.
Parent Tables
Table | Location |
---|---|
Requisition Line Table | Purchases and Payables |
Requisition Line Table | Manufacturing |
See Also
Reference
Operation No.
Next Operation No.
Planning Worksheet
Routing
Other Resources
How to: Create Routings
How to: Create Routing Links
About Production Orders