Share via


Efficiency Field, Prod. Order Capacity Need Table

Specifies the efficiency of the production order capacity need.

It is possible for a work center or machine center to utilize 100 hours a week but not produce 100 standard hours of work. The workers might be working at a faster or slower pace than the standard working pace, causing the efficiency of the work center to be more or less than 100 %. You can calculate as follows: efficiency = (standard hours of work produced / hours actually worked) * 100 %.

Tip

For more information on how to work with fields and columns, see Work with Data. For assistance in finding specific pages, see Search.

Parent Tables

Table Location
Prod. Order Capacity Need Table Manufacturing
Prod. Order Capacity Need Table Manufacturing

See Also

Reference

Capacity Journal

Other Resources

Refresh Production Order