UpdateProject Method
Records progress on specified tasks.
Syntax
expression**.UpdateProject(All, UpdateDate, Action)**
*expression * Optional. An expression that returns an Application object.
All Optional Boolean. True if all tasks in the active project are updated. False if only the selected tasks are updated. The default value is True.
UpdateDate Optional Variant. The date used to indicate progress.
PjProjectUpdate
Constant |
---|
pj0Or100Percent |
pj0To100Percent |
pjReschedule |
Applies to | Application Object
See Also | UpdateTasks Method