BaselineSave Method
Creates a baseline plan.
Syntax
expression**.BaselineSave(All, Copy, Into, RollupToSummaryTasks, RollupFromSubtasks, SetDefaults)**
*expression *Optional. An expression that returns an Application object.
All Optional Boolean. True if the baseline plan is set for all tasks. False if the baseline plan is set only for the selected tasks. The default value is True.
PjSaveBaselineFrom
Constant | Description |
---|---|
pjCopyCurrent | All scheduling information from the active project |
pjCopyBaseline | Baseline start and baseline finish dates |
pjCopyBaseline1 | Baseline1 start and Baseline1 finish dates |
pjCopyBaseline2 | Baseline2 start and Baseline2 finish dates |
pjCopyBaseline3 | Baseline3 start and Baseline3 finish dates |
pjCopyBaseline4 | Baseline4 start and Baseline4 finish dates |
pjCopyBaseline5 | Baseline5 start and Baseline5 finish dates |
pjCopyBaseline6 | Baseline6 start and Baseline6 finish dates |
pjCopyBaseline7 | Baseline7 start and Baseline7 finish dates |
pjCopyBaseline8 | Baseline8 start and Baseline8 finish dates |
pjCopyBaseline9 | Baseline9 start and Baseline9 finish dates |
pjCopyBaseline10 | Baseline10 start and Baseline10 finish dates |
pjCopyStart_Finish1 | Dates in the Start1 and Finish1 custom fields |
pjCopyStart_Finish2 | Dates in the Start2 and Finish2 custom fields |
pjCopyStart_Finish3 | Dates in the Start3 and Finish3 custom fields |
pjCopyStart_Finish4 | Dates in the Start4 and Finish4 custom fields |
pjCopyStart_Finish5 | Dates in the Start5 and Finish5 custom fields |
pjCopyStart_Finish6 | Dates in the Start6 and Finish6 custom fields |
pjCopyStart_Finish7 | Dates in the Start7 and Finish7 custom fields |
pjCopyStart_Finish8 | Dates in the Start8 and Finish8 custom fields |
pjCopyStart_Finish9 | Dates in the Start9 and Finish9 custom fields |
pjCopyStart_Finish10 | Dates in the Start10 and Finish10 custom fields |
PjSaveBaselineTo
Constant | Description |
---|---|
pjIntoBaseline | All baseline information in the active project |
pjIntoBaseline1 | Baseline1 start and Baseline1 finish dates |
pjIntoBaseline2 | Baseline2 start and Baseline2 finish dates |
pjIntoBaseline3 | Baseline3 start and Baseline3 finish dates |
pjIntoBaseline4 | Baseline4 start and Baseline4 finish dates |
pjIntoBaseline5 | Baseline5 start and Baseline5 finish dates |
pjIntoBaseline6 | Baseline6 start and Baseline6 finish dates |
pjIntoBaseline7 | Baseline7 start and Baseline7 finish dates |
pjIntoBaseline8 | Baseline8 start and Baseline8 finish dates |
pjIntoBaseline9 | Baseline9 start and Baseline9 finish dates |
pjIntoBaseline10 | Baseline10 start and Baseline10 finish dates |
pjIntoStart_Finish1 | Dates in the Start1 and Finish1 custom fields |
pjIntoStart_Finish2 | Dates in the Start2 and Finish2 custom fields |
pjIntoStart_Finish3 | Dates in the Start3 and Finish3 custom fields |
pjIntoStart_Finish4 | Dates in the Start4 and Finish4 custom fields |
pjIntoStart_Finish5 | Dates in the Start5 and Finish5 custom fields |
pjIntoStart_Finish6 | Dates in the Start6 and Finish6 custom fields |
pjIntoStart_Finish7 | Dates in the Start7 and Finish7 custom fields |
pjIntoStart_Finish8 | Dates in the Start8 and Finish8 custom fields |
pjIntoStart_Finish9 | Dates in the Start9 and Finish9 custom fields |
pjIntoStart_Finish10 | Dates in the Start10 and Finish10 custom fields |
RollupToSummaryTasks Optional Boolean. True if parent summary task baseline data are rolled up from selected summary tasks.
RollupFromSubtasks Optional Boolean. True if summary task baseline data are rolled up from subtasks.
SetDefaults Optional Boolean. True if the values of RollupToSummaryTasks or RollupFromSubtasks are used as default values for new projects.
Remarks
RollupToSummaryTasks and RollupFromSubTasks will only have an effect if All is false.
Applies to | Application Object
See Also | BaselineClear Method | UpdateTasks Method