<BCWP> Element
BCWP is the Budgeted Cost of Work Performed.
For a <Task>, it is the cumulative value of the task's timephased percent complete multiplied by the task's timephased baseline cost, up to the status date or today's date.
For a <Resource>, it is the rolled-up summary of a resource's BCWP values for all assigned tasks, calculated up to the status date or today's date.
For an <Assignment>, it is the budgeted cost of the work performed on the assignment to date.
For a <Baseline> in a <Task>, it is the cumulative value of the task's timephased percent complete multiplied by the task's timephased baseline cost, up to the status date or today's date.
For a <Baseline> in a <Resource>, it is the budgeted cost of the work performed by the resource on the project to-date.
For a <Baseline> in an <Assignment>, it is the budgeted cost of the work performed on the assignment to-date.
Element Properties
Property | Value |
---|---|
Data Type | Decimal |
Minimum Occurrences | 0 |
Maximum Occurrences | 1 |
Default Value | N/A |
Abstract | False |
Nillable | False |
Element Constraints | N/A |
Parent Elements
Task
Resource
Assignment
Baseline
See Also
XML Schema for the <Task> Element
XML Structure for the <Task> Element
XML Schema for the <Resource> Element
XML Structure for the <Resource> Element
XML Schema for the <Assignment> Element
XML Structure for the <Assignment> Element
<Baseline> Element
<BCWS> Element
<PhysicalPercentComplete> Element