Share via


<FixedCostAccrual> Element

Indicates how fixed costs are to be charged, or accrued, to the cost of a task.

Element Properties

Property Value
Data Type Integer
 
1 Start; costs are accrued as soon as the task starts, as indicated by a date entered in the ActualStart field.
2 Prorated (default); costs accrue as work is scheduled to occur and as actual work is reported.
3 End; costs are not incurred until remaining work is zero.
Minimum Occurrences 0
Maximum Occurrences 1
Default Value N/A
Abstract False
Nillable False
Element Constraints N/A

Parent Elements

Task

See Also

XML Schema for the <Task> Element
XML Structure for the <Task> Element