<LateStart> Element

The latest date that a task can start without delaying the finish of the project.

Element Properties

Property Value
Data Type DateTime
Minimum Occurrences 0
Maximum Occurrences 1
Default Value N/A
Abstract False
Nillable False
Element Constraints N/A

Parent Elements

Task

See Also

XML Schema for the <Task> Element
XML Structure for the <Task> Element