TaskDependencies.Add Method
Project Developer Reference |
Adds a TaskDependency object to TaskDependencies collection.
Syntax
expression.Add(From, Type, Lag)
expression A variable that represents a TaskDependencies object.
Parameters
Name | Required/Optional | Data Type | Description |
---|---|---|---|
From | Required | Object | The Task object specified becomes a predecessor of the task specified with expression. |
Type | Optional | Long | The type of relationship between the linked tasks. Can be one of the PjTaskLinkType constants. The default value is pjFinishToStart. |
Lag | Optional | Variant | The duration of lag time between linked tasks. To specify lead time between tasks, use a negative value. String values default to days unless otherwise specified. Non-string values are interpreted as minutes. The default value is 0. |
Return Value
TaskDependency