Task.LinkSuccessors Method
Project Developer Reference |
Adds successors to a task.
Syntax
expression.LinkSuccessors(Tasks, Link, Lag)
expression A variable that represents a Task object.
Parameters
Name | Required/Optional | Data Type | Description |
---|---|---|---|
Tasks | Required | Object | The Task or Tasks object specified becomes a successor of the task specified with expression. |
Link | Optional | Long | A constant that specifies the relationship between tasks that become linked. Can be one of the PjTaskLinkType constants. The default value is pjFinishToStart. |
Lag | Optional | Variant | A string that specifies the duration of lag time between linked tasks. To specify lead time between tasks, use an expression for Lag that evaluates to a negative value. |
Return Value
Nothing
Example
The following example create a couple of tasks and links one as successor.
Visual Basic for Applications |
---|
|
See Also