ProjectDataSet.TaskRow.TASK_PHY_PCT_COMP Property
Task physical percent of work complete can be used as an alternative for calculating the budgeted cost of work performed (TASK_BCWP).
Namespace: WebSvcStatusing
Assembly: ProjectServerWebServices (in ProjectServerWebServices.dll)
Syntax
'Declaration
Public Property TASK_PHY_PCT_COMP As Integer
Get
Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As Integer
value = instance.TASK_PHY_PCT_COMP
instance.TASK_PHY_PCT_COMP = value
public int TASK_PHY_PCT_COMP { get; set; }
Property Value
Type: System.Int32
Remarks
TASK_PHY_PCT_COMP is not a calculated field and must be entered.